Evening view of the Markovitz pool after the remodel: new glass tile, laminar jets and the marble deck in front of the estate
Jupiter, Florida · Admirals Cove · Infinity-edge remodel · Completed May 2025

An infinity pool brought back to new

The Markovitz residence, a French-style estate on the water in Jupiter, already had a formal infinity pool. It no longer looked the part. Liberty Pools stripped the edge wall, spa and waterline back to the shell, re-waterproofed and re-tiled them in glass, rebuilt the coping, replaced the entire deck in marble with a custom inlay pattern, and added laminar jets, color LED lighting and a code-compliant main drain, working directly for the owner in an occupied home.

2,080SFDeck rebuilt in marble, custom layout
6Laminar jets with integrated LED
185LFCustom step overhang for LED lighting
4moOn site, January to May 2025
The brief

Make an existing pool look like it was built with the house

The architecture set the rules: symmetry, stone, arches and a view straight through the house to the water. The pool sat on that axis, but its gutter wall, spa and deck had aged. The owner wanted it dark and still by day, alive at night, and finished to the standard of the home, without rebuilding the shell.

Liberty Pools contracted directly with the owner (a "Local Magazine" lead, not a referral) and carried the whole scope: leak detection, structural reinforcement of the beam, waterproofing and tile, coping, deck, hydraulics, equipment, lighting and water features.

Design

Dark by day, lit by night

Jan 6, 2025 · Re-tiled, before the fillThe empty pool after re-tiling: new iridescent glass mosaic on the walls and steps, new marble coping
Jan 6, 2025 · Spa and edge wallThe re-tiled spa and infinity-edge gutter wall before water
DayDaytime view across the dark glass-tile pool to the waterway, with the new marble deck and black inlays
NightNight aerial of the pool glowing blue between the wings of the estate
Edge
Existing infinity-edge wall with gutter spillway and collection basin; wall stripped, waterproofed with RedGuard and re-tiled
Interior tile
Iridescent glass mosaic on the edge wall, spa walls, sundeck transition and 6" waterline; full regrout in epoxy grout; existing tile repaired elsewhere
Coping
Existing beam reinforced and the entire coping redone
Deck
Old deck and turf removed; about 2,080 SF rebuilt in marble on a leveled, compacted base with a custom inlay layout, marble baseboard and premium sealer
Water features
6 laminar jets set into the deck with LED, on 150 LF of new electrical run
Hydraulics
New dual-channel main drain on 130 LF of plumbing, compliant with entrapment-prevention code; leak detection and repair included
Equipment
Jandy FloPro 2.7 THP variable-speed pump with iQPUMP Wi-Fi control; Jandy CS200 cartridge filter
Lighting
Jandy HydroCool RGBW nicheless LED, color-changing; 185 LF custom step overhang housing LED strips; new conduit cut into the deck
Craft

Details you only see up close

Close view of the iridescent glass mosaic around a nicheless LED light

Glass over a waterproofed wall

The old tile came off the gutter walls down to the shell. RedGuard waterproofing went on first, then the new glass mosaic, then the spillway was rebuilt so the sheet of water runs evenly into the gutter again.

Laminar jets arcing into the pool with the lit house behind

Laminar jets on the axis

Six jets set into the new deck, aligned with the arches of the house, each with its own LED so the arcs read at night. Two were re-leveled after the owner's walk-through.

Mason setting a black stone inlay into the marble deck

Marble with black inlays

The deck pattern was custom-drawn for the site: light marble with black diamond accents laid out from the pool's centerline, marble baseboard at the walls, one coat of premium sealer to finish.

The build

Scope agreed in stages, work done in one campaign

The owner started with the edge wall and deck, then added spa, waterline and sundeck tile, lighting, a larger deck and the fence work as the project took shape. Every addition was a signed estimate or change order before it was built.

The infinity-edge gutter wall stripped and re-tiled in glass
Sep 2024 – Jan 2025

Strip, waterproof, tile

Contract signed September 4. Old tile off the gutter walls and spa, RedGuard applied, new glass mosaic set on the edge wall, spa, sundeck and waterline.

New marble deck with black inlays laid out in front of the arches
Sep 2024 – Jan 2025

Coping and marble deck

Beam reinforced, coping redone, old deck and turf removed, new marble laid on a leveled base with the custom inlay pattern and new conduit for jets and lights.

Water rising over the new glass tile during the fill
Jan 13 – 15, 2025

Sealer, fill, start-up

Deck sealed, pool filled January 13–14, pump and filter started, deck cleaned. Owner walk-through the same week, punch items logged.

Painters' scaffolding under the loggia next to the new deck
Jan 2025

Sharing the site

Ceiling painters and a lighting crew worked the same weeks; Liberty sequenced sealer, fill and clean-up around them and kept the owner posted daily.

The finished pool and deck seen from the house, with the estate's arches behind
Mar 4 – May 1, 2025

Deck extended, job done

A further 760 SF of marble, baseboard, sealer and fence reinstalled; deck repair April 29; basin tile finished and the job logged as done May 1.

Challenges & solutions

Remodeling a pool nobody wants to rebuild

Challenge

An existing shell with unknowns: possible leaks, a beam that had to carry new coping, and old tile bonded to the gutter walls.

Solution

Leak detection with repairs written into the contract, the beam reinforced before coping, and the edge wall stripped to the shell and waterproofed with RedGuard before a single new tile went on.

Challenge

The original main drain did not meet current entrapment-prevention code.

Solution

Replaced with a new dual-channel main drain on 130 feet of new plumbing, so the remodeled pool complies with today's safety standard, not the one it was built to.

Challenge

An occupied estate with other trades in the same weeks: ceiling painters over the pool, a lighting crew waiting on the deck sealer, scaffolding and tools left on new marble.

Solution

Liberty sequenced the sealer, the fill, the equipment start-up and the deck clean-up around the other contractors' dates and kept the owner informed daily until the deck was clear.

Challenge

The scope roughly doubled over the project as the owner saw the results and asked for more.

Solution

Four additional estimates and one change order, each signed before the work started, so the owner always knew what was being built and the crew never worked from a verbal instruction.

Film

The pool at night

A short film of the finished project after dark: laminar jets, the re-tiled edge and the color lighting against the estate.

Tap to play with sound. 70 seconds.

Site clip · May 1, 2025

The basin, tiled and signed off

Raw phone footage from the project manager on the last day on site: the collection basin behind the infinity wall, fully tiled in the same glass mosaic as the pool. This is the clip that closed the job in our system.

Tap to play. 40 seconds, no sound.

The result

Handed over, and photographed with the owner

Daytime view down the pool axis toward the main house, jets running
Homeowner Alan Markovitz with Liberty Pools CEO Lucas Garcia at the finished pool
Night view along the pool edge with the lit arches of the house
The re-tiled spa and its spillover before the fill

Alan Markovitz with Liberty Pools CEO Lucas Garcia at the finished pool, Jupiter, 2025. Finished photography January to March 2025; construction photos from the Liberty project record, January to May 2025.

For Kolter Homes

What this project proves

We renovate as carefully as we build

Existing structure, unknown history, an owner living on site. Diagnose first, waterproof before finish, and reinforce what carries load.

We bring pools up to code

A remodel is the moment to fix what a new buyer will inherit: entrapment-compliant drains, new conduit, modern variable-speed equipment with app control.

Our owners keep adding scope

Four approved additions and a change order on one project, every one signed first. That is what trust looks like on paper.