A free-form infinity pool built on 51 helical piles at the tip of a peninsula lot, finished entirely in emerald porcelain, and delivered as a subcontractor to the general contractor in under six months from dig to final inspection.
The residence sits on a narrow peninsula with water on three sides. The owner and the general contractor, Buss Construction Services, wanted a pool that would read as an extension of the waterway: a long, free-form body of water with a vanishing edge along the entire north-east side, a dry lounge sunk into the pool, and a single dark-green material running from the floor of the pool up over the coping.
Liberty Pools was brought in as the pool subcontractor. Our scope ran from engineering and permitting with the City of Hollywood through structure, waterproofing, tile, equipment and start-up, coordinated week by week with the GC's own trades on site.
The geotechnical report ruled out a conventional slab-on-grade shell. The pool, the 85-foot collection basin and the dry lounge all sit on 51 helical piles rated at 12 tons in compression, tied into a shell poured at 6,000 PSI with 10-inch walls and a 12-inch floor on double-layer #5 rebar. Because the site is in flood zone AE, the shell carries hydrostatic relief and the plans were sealed for the city's structural review.
The water feature is a true vanishing edge, not a spillway: 78 linear feet of wall drop into a gutter and an 85-foot basin with its own pump, filter, channel drain and autofill, feeding four dedicated return lines so the sheet of water stays continuous in wind.

Sheet 1 of 4, approved 03/04/2026. Sealed engineering plans reviewed and stamped by the City of Hollywood building department.
Every milestone below was scheduled, photographed and inspected through our project-management system. The owner and the GC could follow each stage from their phones.

Dig day March 4. Steel and bonding inspected March 16, shell shot by March 24.

Perimeter plumbing passed April 1; equipotential bond passed April 24.

Seven weeks to set 3,500 SF of porcelain over a full LATICRETE membrane system.

Two variable-speed pumps, automation, salt systems and heaters set; pool filled July 3.

Coping and deck complete August 15. Electrical, deck, barrier and city finals passed by August 29.

A full-tile interior is rare in South Florida. The shell was prepped, coated twice with HydroBan and fabric at every transition, then tiled with 254 Platinum and epoxy grout so the finish holds up to salt water for decades.

The vanishing wall was ground and levelled to a single line over 78 feet, then wrapped in tile and finished with an LED strip along the full gutter edge so the sheet of water reads at night.

A 16' × 13' dry lounge sunk into the pool, finished in sandblasted emerald marble on floor, edge and wall, with six 8-inch risers carrying guests down into the water.
Fill soil on a waterfront peninsula, inside flood zone AE. A standard shell would settle and crack.
Soil report before design, then 51 helical piles under pool, basin and lounge, with existing piles located and tied in. No settlement, no cost surprises during excavation.
Only a 5-foot side access to the back of the lot for machinery.
Excavation with a compact Bobcat in a 7-foot working lane. All excavated material was reused as fill on site, so no truck convoy through the neighborhood.
The landscape architect raised the retaining wall and the landing after the shell was shot.
Beam and entry steps were raised with new rebar to meet the new elevations, priced as a change order and built without pushing the schedule.
Tiling an entire pool interior with porcelain, a finish that fails if the waterproofing is even slightly wrong.
A written, step-by-step LATICRETE specification in the contract, a dedicated tile crew for seven weeks, and coordination with the GC's electrician for the LED runs.
Rafael, Liberty Pools' project manager on Southlake, on what has to be right before anyone digs a waterfront pool. Every Liberty project has one PM from permit to pool school.
Tap to play. Recorded on site in July 2026.




Pool school with the owner completed September 8, 2026. A second Liberty crew is now setting 5,800 SF of granite driveway and 3,500 SF of travertine decking on the same property.
Southlake was delivered as a subcontractor to Buss Construction: their schedule, their site rules, their electrician. We are used to being one trade among many.
Sealed plans, geotechnical-driven foundations, a hydrostatic-relief shell and seven passed municipal inspections on a difficult waterfront lot.
Dig to final city inspection in under six months on a 32,750-gallon infinity pool, with every stage logged and visible to the client.