The Schwimmer residence started with a tired pool, a cracked deck and an outdoor kitchen past its life. Liberty Pools demolished all of it and delivered a new pool, raised spa, fire-and-water table, outdoor kitchen, pergola, marble deck and turf, on one permit and one schedule.


The existing pool, deck and kitchen were demolished on October 21–22, 2025. Everything in the right-hand photo was built by Liberty Pools and its trade partners in the nine months that followed.
Every Liberty project starts with a 3D model of the finished yard. The renders below were approved by the Schwimmers in October 2025; the photos were taken in July 2026.


Permit and HOA approval came first, then demolition. From there the job ran through the same inspected sequence Liberty uses on every pool, with each step photographed for the owner.

Old pool and deck out in two days. New pool excavated October 23, steel and main drain inspected October 31.

Gunite the first week of November, plumbing and equipotential bond inspected and passed by January 6.

1,320 SF of marble set and sealed, waterline tile installed, deck inspection passed May 27.

Fire table and LED stepping stones set, turf laid, finish applied June 23–26 and the pool filled June 29.

Safety barrier and final city inspections passed August 12. Pool school with the owners August 14–21.
A renovation, not a blank lot: an existing pool, deck, kitchen, sprinklers and roots had to come out without damaging the house, the lanai or the neighbors' walls.
A dedicated demolition partner, a dumpster plan agreed with the owner in advance, roots and grade cleared before excavation, and the lanai wall sealed and re-slatted as part of the scope.
HOA plus city permitting, and a plumbing inspection that failed on its first attempt in December.
HOA and permit secured before a shovel went in. The failed item was corrected and re-inspected within days, and the equipotential bond passed on the first try.
The owners changed their minds mid-build: a wider pool, a different deck layout, more turf, more planters.
Each change was priced as a written change order, the engineering and city revisions were filed, and the schedule absorbed them without reopening the permit.
Six trades on one small backyard: demo, shotcrete, electrical, gas, marble, turf, carpentry.
One Liberty project manager sequenced every trade and every inspection; the owners followed progress and photos from their phones and never had to chase a subcontractor.
The owner, standing in his finished backyard, on the process, the crew and the result.
Recorded at the residence, 2026 · 48 seconds
Tap to play with sound.




Pool school completed August 21, 2026. The owners have since come back to Liberty for a follow-up project on the same pool.
Pool, spa, fire and water features, kitchen, pergola, deck and turf under one contract and one permit. A buyer gets one point of contact, not six.
3D renders approved before permitting, and the built result matches them. That is how we keep buyers confident and change orders small.
HOA, city permit, seven inspections and three plan revisions on a renovation site, all closed out with a final city inspection and a documented hand-over.